Brevard County LFGE Plant

CCC Group performed as the General Contractor in the on budget and on-time completion of a new 9.6MW Landfill Gas to Energy plant.

Scope of work included all site development, underground utilities, LFG tie-in, concrete foundations, power and controls installation, equipment installation, process piping as well as the building architectural, area paving and fencing.

Equipment installation included the placement and tie in of 6 ea. Cat 3520C Gen-Sets, complete with radiators, roof mounted silencers, gas filtration and compression equipment, switchgear and transformer required for connection to the local utility. The scope also included utility piping systems for services such as air, lube oil and waste oil.

Building construction utilized load bearing filled block walls with steel roof framing and an insulated membrane roof.